Robertson Road will be closed to through traffic for four days beginning Monday, Jan. 26, running through Thursday, Jan. 29.

The closure will be located just to the south of the intersection of Robertson Road and Painted Horse Trail.

Residents who live south of Painted Horse Trail should exit Robertson Road by going south to CY Avenue. Those who live at Painted Horse Trail or north should use Robertson Road north.

No access to any residences will be restricted during this closure.

Currently there are portable message signs activated in the area advising drivers of the upcoming closure.

This closure is to allow crews to install water lines and storm sewer as part of the overall Robertson Road reconstruction project.

The closure will last 24 hours per day, beginning Monday morning. Once this work is completed, there are no further closures of Robertson Road expected due to this construction project until the school year has ended. The entire project is scheduled to be completed July 31.

 

 